    A team member notifies the project manager that the activities comprising the work package are no longer appropriate. It would be BEST for the Project Manager to be in which part of the Project Management Process?

    a) Corrective Action
    b) Integrated Change Control
    c) Monitoring & Controlling
    d) Project Closing

    #4875
    admin
    Keymaster

    The correct answer is C.

    If you chose another part of the project management process, you probably forgot that the situation needs to be evaluated by the project manager before recommending a change or entering integrated change control.