The correct answer is D.
The two paths you have in this question are Start, 1, 2, 3, End and Start, 1, 4, End. Path Start, 1, 2, 3, End would take 1 + 4 + 5 days or 10 days to complete. Path Start, 1, 4, End would take 1 + 10 days or 11 days to complete. A trick to calculating this quickly is to carefully draw the network diagram, list all the possible paths and then determine how much time each path would take.