    The sponsor has informed you that the resources for your project will be cut. The sponsor will want to know how long the project will take if only nine resources each month are committed to your project. What is this activity called?

    A Crashing
    B Floating
    C Leveling
    D Fast tracking

    #4793
    admin
    Keymaster

    The correct answer is C.

    Resource leveling refers to keeping the number of resources the same and letting time and cost be flexible.