    A new software development project is in progress and the project manager is working with the quality assurance department. They want to improve everyone’s confidence that the project will satisfy quality standards. Which of the following MUST they have before they start this process?

    a) Completed checklists
    b) A quality control plan
    c) Result of quality control measurements
    d) Rework

    #4231
    admin
    Keymaster

    The correct answer is C.

    The only choice listed that makes sense and is an input to Manage Quality is choice C.