    A project manager receives a change request from the customer. The change requires adding a new filtration system to the project in place of cleaner bag. When the project manager evaluates the change, it is MOST important that she considers the impact on the:

    a) Project Constraints
    b) Communication Management Plan
    c) Sponsor
    d) Subsequent Activities

    #4089
    admin
    Keymaster

    The correct answer is A.

    Major project constraints include scope, time, cost, quality, risk, resources, and customer satisfaction. This question talks about a change in scope. It would be most important to look for impacts to other project constraints. After that is completed, the impact to subsequent work packages would be evaluated.

    Pass PMP in the First Attempt : PMP Strategy

    Revise PMP ConceptsPMP Concepts

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.