    A parking lot fencing project was bid at US$11 per foot , and the company is doing all the work. The parking lot has four equal sides of 125 feet and requires installation of a 6 foot diameter culvert on one side. Fencing should be installed at a rate of 100 feet per day. The culvert installation will cost US$500 and take one day to complete. The culvert must be installed before work can begin on that side of the fence. After 3 days of work, one side is complete. Another has 75 feet installed, and the culvert is completely installed. AC is $2700. What is the current status of the project?

    a) The budget is neutral with a cost variance of $0
    b) It is over budget, with a cost variance of US$-1000
    c) It is under budget, with a cost variance of +500 due to the completion of the culvert
    installation
    d) It is over budget with a cost variance of US$125

    #4066
    admin
    Keymaster

    The correct answer is A.

    EV is the value of the work completed. In this case, one side is done ($11 x 125 = $1,375), 75 feet of the second side is done ($11 x 75 = $825) and the culvert is complete ($500) for a total of $2,700. Since the AC is $2,700, CV = $0. You are budget neutral.

    Pass PMP in the First Attempt : PMP Strategy

    Revise PMP ConceptsPMP Concepts

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.