During the executing process group of a project, you realize the subcontractors are working with incomplete and different project scope statements. As the project manager what should you do first?
a) Check the work completed against the correct project scope statement
b) Review the scope with the stakeholders
c) Document the inconsistencies to the sponsor, calculating the cost of non conformance
d) Stop work until the scope issue is resolved