    Resource requirements are determined :

    a) Before the project schedule and after the network diagram
    b) After the project schedule and project scope statement
    c) After the project schedule and WBS
    d) Before the project scope statement and network diagrams

    #3617
    admin
    Keymaster

    The correct answer is A.

    This is another question asking about the process of project management.