Home › Forums › PMP Questions and Answers Discussion › Cost Management Question 23 This topic has 2 replies, 2 voices, and was last updated 5 years, 3 months ago by REUBEN. Viewing 3 posts - 1 through 3 (of 3 total) Author Posts January 25, 2020 at 5:52 PM #3510 adminKeymaster Project set up costs are an example of? a) Variable costs b) Fixed costs c) Overhead costs d) Opportunity costs January 25, 2020 at 5:53 PM #3511 adminKeymaster The correct answer is B. Setup costs do not change as production on the project changes. Therefore, they are fixed costs. Pass PMP in the First Attempt : PMP Strategy Revise Cost Management Concepts: Project Cost Management Quiz: 20 Questions Challenge 50 Questions Challenge January 28, 2020 at 3:18 PM #3586 REUBENParticipant B Author Posts Viewing 3 posts - 1 through 3 (of 3 total) You must be logged in to reply to this topic. Log In Username: Password: Keep me signed in Log In