    If the project team is subdividing project work packages into smaller , more manageable components, they are?

    a) Creating a WBS
    b) Decomposing
    c) Network diagramming
    d) Activity sequencing

    #3325
    admin
    Keymaster

    The correct answer is B.

    The important words here are “project work packages.” This indicates that a WBS has already been created. If the question said “project deliverables,” the answer would have been choice A.