Home › Forums › PMP Questions and Answers Discussion › Scope Management Question 23 This topic has 1 reply, 1 voice, and was last updated 5 years, 3 months ago by admin. Viewing 2 posts - 1 through 2 (of 2 total) Author Posts January 8, 2020 at 4:48 PM #3324 adminKeymaster If the project team is subdividing project work packages into smaller , more manageable components, they are? a) Creating a WBS b) Decomposing c) Network diagramming d) Activity sequencing January 8, 2020 at 4:50 PM #3325 adminKeymaster The correct answer is B. The important words here are “project work packages.” This indicates that a WBS has already been created. If the question said “project deliverables,” the answer would have been choice A. Pass PMP in the First Attempt : PMP Strategy Revise Scope Management Concepts: Project Scope Management Quiz: 20 Questions Challenge 50 Questions Challenge Author Posts Viewing 2 posts - 1 through 2 (of 2 total) You must be logged in to reply to this topic. Log In Username: Password: Keep me signed in Log In