The correct answer is C.
This question shows how important historical information is for adequately planning projects. Notice the wording in the question. It is looking for an example. The word “stakeholder” is used in the question, but this is not an example of stakeholder analysis (choice A), nor is it an example of scope management (choice B), as the situation described is from past projects. Such information can lead to risks (choice D), but this is not an example of risk identification.