During the conceptual phase of a pipeline project, the project engineer estimates the following. The cost of the materials is most likely US$100,000, optimistically US$90,000, and pessimistically US$120,000. The cost for labor is most likely US$60,000, optimistically US$50,000, and pessimistically US$70,000. The cost for the construction management fees is most likely US$ US$30,000, optimistically US$20,000, and pessimistically US$40,000.What is the probability of the project coming in under US$270,000.
A) Over 50%
B) Zero
C) Exactly 50%
D) Less than 50%