    Which of the following techniques incorporates a form of risk assessment?

    a) Arrow diagramming method
    b) Network diagramming
    c) Critical path method
    d) 3 point estimation

    #3315
    admin
    Keymaster

    The correct answer is D.

    Three-point estimation is based upon optimistic, realistic ahd pessimistic estimates, which takes into account the risk of not meeting your date.