    The principle use of a pareto chart is to?

    a) Focus attention on the most critical issues
    b) Quantify risks
    c) Help predict future problems
    d) Improve risk management

    #3298
    admin
    Keymaster

    The correct answer is A.

    A Pareto chart helps you identify the most frequently occurring problems and determine which problems to focus your attention on. The result is a higher quality project. It can be used to look at past problems, not to predict future ones (choice C).