Home Forums PMP Questions and Answers Discussion Quality Management Question 21

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #3276
    admin
    Keymaster

    All of the following are examples of Control Quality EXCEPT?

    a) Inspection
    b) Cost of quality
    c) Pareto chart
    d) Fishbone diagram

    #3277
    admin
    Keymaster

    The correct answer is B.

    Choices A, C, and D are done as part of Control Quality (depending on how they are used). This leaves only choice B, which must be the best answer. Cost of quality is part of Plan Quality.

    Pass PMP in the First Attempt : PMP Strategy

    Revise Quality Management Concepts: Project Quality Management

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.