    Two people on the same project team have just found out that they are working on the same work. This situation can best be categorized as lack of?

    a) A good work breakdown structure
    b) Matrix organization
    c) Sponsor direction
    d) Effective status meetings

    #3274
    admin
    Keymaster

    The correct answer is A.

    Though there could be other reasons than those presented, choice A is the best characterization. A good work breakdown structure identifies each work package so that each can be properly assigned, thus reducing the possibility that the same work will be done by more than one resource.