The correct answer is B.
You need to draw a network diagram for this question. This diagram has two paths: Start, 1, 2, 3, End and Start, 1, 4, End. The original length of the first path is 10 and the second is 9, making the first path critical and the length of the critical path 10. If Activity 4 now takes 10 weeks instead of 8, the critical path would change to Start, 1, 4, End and be 11 weeks long.