please let me know details on the question answer below
thanks
You are a project manager on a project that requires 100 items to be tested, spaced evenly over 5 weeks. You have just begun week 3 , with an overall budget of US$10,000. To date you have spent US$2000 with 40 items tested successfully. What does the Cost Variance (CV) tell you during this time?
Project is on budget
Project is getting $2 of the work for every dollar spent
Project is $2000 under budget
The project is proceeding at 100% of the expected rate