Home › Forums › PMP Questions and Answers Discussion › Schedule Management Question 17 This topic has 1 reply, 1 voice, and was last updated 5 years, 4 months ago by admin. Viewing 2 posts - 1 through 2 (of 2 total) Author Posts December 8, 2019 at 4:35 PM #3175 adminKeymaster Which of the following does not need to be done if there is a major delay on a non-critical path activity? a) Investigate the delay b) Re-evaluate which path is critical c) Change the project schedule d) Review the float time for the activity December 8, 2019 at 4:40 PM #3178 adminKeymaster The correct answer is C. You do not necessarily need to change the schedule, unless, of course, the delay is more than the activity’s float. Pass PMP in the First Attempt : PMP Strategy Revise Schedule Management Concepts: Project Schedule Management Quiz: 20 Questions Challenge 50 Questions Challenge Author Posts Viewing 2 posts - 1 through 2 (of 2 total) You must be logged in to reply to this topic. Log In Username: Password: Keep me signed in Log In