Home › Forums › PMP Questions and Answers Discussion › Cost Management Question 19 This topic has 1 reply, 1 voice, and was last updated 5 years, 4 months ago by admin. Viewing 2 posts - 1 through 2 (of 2 total) Author Posts December 4, 2019 at 4:40 AM #3159 adminKeymaster What type of cost is team training? a) Direct b) NPV c) Indirect d) Fixed December 4, 2019 at 4:42 AM #3160 adminKeymaster The correct answer is A. You are training the team on skills required for the project. The cost is directly related to the project and thus a direct cost. Pass PMP in the First Attempt : PMP Strategy Revise Cost Management Concepts: Project Cost Management Quiz: 20 Questions Challenge 50 Questions Challenge Author Posts Viewing 2 posts - 1 through 2 (of 2 total) You must be logged in to reply to this topic. Log In Username: Password: Keep me signed in Log In