The project manager had to request a change in the approved project budget because the WBS did not contain some work that needed to be done. Which of the following is the BEST thing to do as a result of this situation?
a) Redo the WBS and look for more missing scope
b) Ask for a time extension
c) Redo the change control system
d) Recalculate the project scope variance
A change in cost may not affect the time a project takes to complete (choice B). There is nothing in the question to suggest that the methods to find and make changes (choice C) are faulty. Choice D is a made-up term. When such a problem occurs, it is important to see if anything else has been forgotten (choice A).