Home › Forums › PMP Questions and Answers Discussion › Schedule Management Question 16 This topic has 1 reply, 1 voice, and was last updated 5 years, 5 months ago by admin. Viewing 2 posts - 1 through 2 (of 2 total) Author Posts November 24, 2019 at 6:19 AM #2758 adminKeymaster Rearranging resource so that a constant number of resources is used each month is called? a) Crashing b) Floating c) Leveling d) Fast tracking November 24, 2019 at 6:21 AM #2760 adminKeymaster The correct answer is C. The key to this question is the phrase “constant number used each month.” Only leveling, choice C, has such an effect on the schedule. Pass PMP in the First Attempt : PMP Strategy Revise Schedule Management Concepts: Project Schedule Management Quiz: 20 Questions Challenge 50 Questions Challenge Author Posts Viewing 2 posts - 1 through 2 (of 2 total) You must be logged in to reply to this topic. Log In Username: Password: Keep me signed in Log In