    Rearranging resource so that a constant number of resources is used each month is called?

    a) Crashing
    b) Floating
    c) Leveling
    d) Fast tracking

    #2760
    admin
    Keymaster

    The correct answer is C.

    The key to this question is the phrase “constant number used each month.” Only leveling, choice C, has such an effect on the schedule.