    Project set up costs are an example of?

    a) Variable costs
    b) Fixed costs
    c) Overhead costs
    d) Opportunity costs

    #2691
    admin
    Keymaster

    The correct answer is B.

    Setup costs do not change as production on the project changes. Therefore, they are fixed costs.

    Pass PMP in the First Attempt : PMP Strategy

    Revise Cost Management Concepts: Project Cost Management