    All the following details are mentioned in the stakeholder register EXCEPT?

    a) Stakeholder requirements
    b) Identification information
    c) Assessment information
    d) Stakeholder classification

    #2669
    admin
    Keymaster

    Correct answer is a.

    Stakeholder requirements are collected during Collect requirements process and mentioned in the Requirements Documentation.