A project team has been arguing for days about the correct way to complete a high level design. This argument has caused a schedule performance index (SPI) to fall to 0.89 and the Cost Performance Index (CPI) to 0.8. if the project manager tells the team, “we will schedule this discussion for our team meeting next week”, the project manager is?
a) Using earned value
b) Compromising
c) Increasing costs even further
d) Withdrawing