    You are finalizing the monthly project status report due now to your manager when you discover that several project team members are not reporting actual hours on project archives. This results in skewed project statistics. What is the MOST appropriate action to be taken?

    a) Discuss the impacts of these actions with the team members
    b) Report the team member’s actions to the functional managers
    c) Continue reporting information as presented to you.
    d) Provide accurate and truthful representations in all project reports

    #2544
    admin
    Keymaster

    The correct answer is D.

    The project manager’s responsibility is to provide truthful project information. He or she should thereafter discuss the impacts of their actions with the team members. If that does not work, the next step is to report it to their functional managers.

    Pass PMP in the First Attempt : PMP Strategy

    Revise Communication Management ConceptsProject Communication Management

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.