Home › Forums › PMP Questions and Answers Discussion › Schedule Management Question 15 This topic has 1 reply, 1 voice, and was last updated 5 years, 5 months ago by admin. Viewing 2 posts - 1 through 2 (of 2 total) Author Posts November 12, 2019 at 12:27 PM #2540 adminKeymaster What is the duration of milestone? a) Shorter than the duration of the longest activity b) Shorter than the activity it represents c) There is no duration d) Same length as the activity it represents November 12, 2019 at 12:29 PM #2541 adminKeymaster Correct answer is c. There is no duration for the milestone. Pass PMP in the First Attempt : PMP Strategy Revise Schedule Management Concepts: Project Schedule Management Quiz: 20 Questions Challenge 50 Questions Challenge Author Posts Viewing 2 posts - 1 through 2 (of 2 total) You must be logged in to reply to this topic. Log In Username: Password: Keep me signed in Log In