    Q> The project manager is involved in the Develop Schedule process for the project. He has analysed the project, compressed the schedule, and completed a Monte Carlo Analysis, which of the following is an output of develop schedule?

    Ans- why Change request is showing an incorrect answer. its an output of develop schedule.

    #2520
    admin
    Keymaster

    Thanks for pointing it out. Will update the question. Resource Requirement & Change Requests both are the correct answers.