You are in the middle of a 2 year project to deploy new technology to field offices across the country. A hurricane caused power outages just when the upgrade was near completion. When the power was restored, all of the project reports and historical records were lost with no way of retrieving them. What should have been done to prevent this problem?
a) Purchase insurance
b) Plan for a reserve fund
c) Monitor the weather and have a contingency plan
d) Schedule the installation outside of hurricane season