    Another project has had a major defect. A project manager has gotten his project team and the process engineers involved in analyzing how this might affect their project. Which of the following would BEST describe what the group is involved in?

    a) Quality Analysis
    b) Plan quality management
    c) Manage quality
    d) Perform quality control

    #2417
    admin
    Keymaster

    The correct answer is B.

    The group is using organizational process assets to improve their project. Although the incident just occurred, it was on another project. They are in the Plan Quality process.