  • #2410
    admin
    Keymaster

    You have just found that a major subcontractor of your project consistently provides deliverables late. The subcontractor approaches you and asks you to continue accepting late deliverables in exchange for a decrease in project costs. This offer is an example of?

    a) Confronting
    b) Compromise
    c) Smoothing
    d) Forcing

    #2411
    admin
    Keymaster

    The correct answer is B.

    Both parties are giving up something. This is a compromise.

    Pass PMP in the First Attempt : PMP Strategy

    Revise Resource Management Concepts: Project Resource Management