    During Scrum Retrospective, development team analyzed one of the process which they want to improve in the next sprint. They created the plan on how to improve the process efficiency. Where would the team place the work involved in this improvement plan?

    A. Product Backlog
    B. Sprint Backlog
    C. Retrospective Improvement Backlog
    D. Since the development team is self-organizing and self-directing, they just do the work involved in the improvement plan in the next sprint

    #24093
    admin
    Keymaster

    Correct answer is B.

    All improvement goals which the development team planned to take up in upcoming sprints are placed in the sprint backlog.

    PMP/Agile Useful Resources : PMP/Agile Resources

    World of Project Management : Mobile App

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

    #24129
    Daniel
    Guest

    At this point in time, the development team is at the end of the current sprint. Hence, the sprint backlog of the coming sprint doesn’t exist. But the product backlog does. Moreover, the development team cannot dictate which story points to prioritize . They need the say of the product owner. In turn, the product owner prioritizes only the items in the product backlog. In summary, under the given conditions,it looks the product backlog is the place for the process improvement effort than sprint backlog

    #24131
    Chris
    Guest

    I would disagree, I believe the correct answer is A. The sprint ends after the retrospective. Items are not carried directly between sprints. Any outstanding items in the sprint backlog are returned to the product backlog, where they are eligible to be selected for the next sprint.