    During a voice conference, one team member suggests that a more experienced person be used on the project. Another talk about using a person with more training. Which of the following BEST describes what is being done?

    a) Plan risk responses
    b) Resource Leveling
    c) Define activities
    d) Develop team

    #2406
    admin
    Keymaster

    The correct answer is A.

    Resource leveling (choice B) involves analysis of the number of resoures used. Choice C occurs before the team is selected. Choice D occurs after the team has been selected. The team is trying to respond to a risk by changing a resource. The answer is choice A.

    Pass PMP in the First Attempt : PMP Strategy

    Revise Risk Management Concepts: Project Risk Management

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.