    All the following are the steps of stakeholder analysis EXCEPT:

    A. Develop appropriate management strategies to effectively engage stakeholder throughout the
    project life cycle.
    B. Identify all the potential stakeholders and relevant information, such as their roles, departments, interests, knowledge, expectations, and influence levels.
    C. Analyze the potential impact or support each stakeholder could generate, and classify them to
    define approach strategy.
    D. Assess how stakeholders are likely to react or respond in various situations, in order to plan how to influence them to enhance their support and mitigate potential negative impacts.

    #2398
    admin
    Keymaster

    Stakeholder analysis follows 3 steps as described under choices B, C, and D. activity described under choice A is performed during Plan Stakeholder Engagement process.

    Pass PMP in the First Attempt : PMP Strategy

    Revise Stakeholder Management Concepts: Project Stakeholder Management

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.