    How is three point estimating related to risk?

    A It tells your how much assumption testing is required
    B It states whether the risk estimate is acceptable
    C It indicates the estimate degree of uncertainty
    D It indicates the risk variance

    #2390
    admin
    Keymaster

    The correct answer is C.

    The wider the range between the optimistic and pessimistic estimates in a three-point estimate, the more uncertainty the estimator has.