    In Agile, velocity helps to know how much a team can accomplish in future iterations. Which of the following is NOT true about velocity?

    a. It measures the team’s capacity for work per iteration
    b. It varies the most during the first few iterations
    c. It stabilizes after a few iterations
    d. It always increases with time as the team members get habitual of working with each other

    #23706
    admin
    Keymaster

    Correct answer is D.

    Velocity gets stabilized with time as team needs to maintain, refactor, and support already developed and deployed solutions. Moreover, sometimes team adds some improvement activities decided in retrospective meetings in the iteration which also let team pick up fewer story points for the iterations.

    PMP/Agile Useful Resources : PMP/Agile Resources

    World of Project Management : Mobile App

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.