The correct answer is B.
The wording of this question can be confusing. Reserve (choice A) is mentioned in the situation, but the project manager is not dealing with reserves in the actions he is taking. Verify Scope (choice C) involves meeting with the customer to gain formal acceptance, so it cannot be the best choice. Choice D cannot be the best choice since the project manager is trying to make something good happen, not dealing with a negative impact, or threat, that may or may not occur. The project manager is working to make a positive impact on the project more likely to occur, therefore choice B is best.