Home › Forums › PMP Questions and Answers Discussion › Integration Management Question 11 This topic has 1 reply, 1 voice, and was last updated 5 years, 6 months ago by admin. Viewing 2 posts - 1 through 2 (of 2 total) Author Posts October 10, 2019 at 8:23 AM #2348 adminKeymaster All of the following are purposes of project charter except? a) It establishes the project b) It identifies the product acceptance criteria c) It gives the project manager authority d) It includes stakeholder’s requirements October 10, 2019 at 8:25 AM #2349 adminKeymaster The correct answer is B. Product acceptance criteria is included in the project scope statement. Revise Project Integration Management Concepts: Project Integration Management Quiz: 20 Questions Challenge 50 Questions Challenge Author Posts Viewing 2 posts - 1 through 2 (of 2 total) You must be logged in to reply to this topic. Log In Username: Password: Keep me signed in Log In