Team is tracking project’s risk profile through cumulative risk severity stacked graph. Team observed there is rise in the graph. All of the following can be the reasons except:
a. New risk emerged but its probability is low
b. New risk emerged but its probability is high
c. Probability of the existing risk increases
d. Probability of the existing risk decreases
Correct answer is D.
Attractive offers on online products
In the Project Risk Severity profile stacked area cumulative graph, if the risk probability of any risk is decreased then the graph goes down.