    All of the following statements about the project feasibility study are True EXCEPT?

    a) They can help in selecting one project over the another
    b) They can be the first project phase or a separate project
    c) They can be used to determine if the project should be completed
    d) They can be used to determine project team members

    #2327
    admin
    Keymaster

    The correct answer is D.

    A feasibility study helps in deciding if the project needs to be undertaken or not and not its team members.