    The project manager should apply expert judgment to decide upon the level of engagement required at
    each stage of the project from each stakeholder. What engagement is required from the stakeholders at the beginning of a project?

    A. Senior stakeholders are required to be highly engaged in order to clear away any obstacles to success. This engagement is called supportive.
    B. Other stakeholders, such as end users are required to review and sign off completed deliverables.
    C. Senior stakeholders are required to be neutral to allow the project manager to complete planning without any hindrance.
    D. Senior stakeholders are required to be highly engaged in order to clear away any obstacles to success. This engagement is called leading.

    #2324
    admin
    Keymaster

    Choice A is partially correct because the name of this engagement is leading, not supportive. Therefore D is the correct choice. In fact the engagement required at the beginning is ‘Leading’. After that it should be ‘Supportive’. Later, stakeholder need to review and sign off the work and deliverables as the work gets completed from phase to phase.

    Revise Stakeholder Management Concepts: Project Stakeholder Management