    Which of the following is the MOST beneficial result of the project manager knowing the critical path?

    a) She would know where extra resources can be placed
    b) She would know what activities she needs to focus on while managing the project
    c) She would know where stakeholders need to be assigned to the project
    d) She would know where there is float on the project

    #2315
    admin
    Keymaster

    The correct answer is B.

    All of these choices could be said to be correct. Which is the MOST correct? Activities on the critical path require more of the project manager’s attention, because delays in these activities will create a delay in the entire project. Since delay has the largest potential to hurt the project, choice B is the best answer.

    Revise Schedule Management Concepts: Project Schedule Management

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.