A project manager is creating a risk response plan. However, every time a risk response is suggested, another risk is identified that is caused by a response. Which of the following is the BEST thing for the project manager to do?
a) Document the new risks and continue the Plan Risk Response Process
b) Make sure the project work is better understood
c) Spend more time making sure the risks responses are clearly defined
d) Get more people involved in the Identify Risks process since the risks have been missed