All of the following are required to bring the project to closure EXCEPT?
a) Perform project feedback with the team
b) Obtain sign off from the customer
c) Review project documentation for completeness
d) Update the project management plan
Choice A refers to lessons learned, and choices B and C are always part of closure. When project closure occurs at the end of the project (as opposed to at the end of a phase), the project management plan would not need to be updated (choice D).