    Which of the following would be the MOST appropriate thing to do during the executing process group?

    a) Determine individual team member performance
    b) Add new skills to team member’s human resources records
    c) Determine Acceptance criteria
    d) Determine how you’ll complete process improvement.

    #2291
    admin
    Keymaster

    The correct answer is A.

    Choice B is part of the closing process group. Choice C occurs during the initiating process group. Since choice D is a planning function, it must take place during the planning process group. Choice A is done in the executing process group, as part of the Manage Project Team process.

    Revise Project Management Fundamentals Concepts: Project Management Fundamentals

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.