    Quality on your project must be as high as possible, yet this type of project is new for your company. Which of the following is the BEST thing to do?

    a) Audit work as it is being completed to look for any needed improvements
    b) Improve your work authorization system
    c) Use cause and effect diagrams when there is a defect.
    d) Make sure your staffing management plan is up to date.

    #2257
    admin
    Keymaster

    The correct answer is A.

    Choice B might help make sure things get done on time and that people know what work they need to do and when, but it is not related to quality. Choice C is looking backward. It is reactive, so it is not the best choice. Choice D deals with when people will be moved on and off the project. It does not deal with quality. Choice A is a better answer because it directly deals with quality.

    Revise Quality Management Concepts: Project Quality Management

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.