    Organization ABC has been following Agile to execute their projects. Recently they started the complex project and the team wants to know high level requirements with approximate plan so that they can start the work. What would you suggest the team to refer to?

    a. Refer the Project Roadmap
    b. Refer the Project Charter
    c. Refer the Product Backlog
    d. Refer WBS

    #22176
    admin
    Keymaster

    Correct answer is A.

    Product Roadmap contains high level plan which roughly depicts what all user stories/epics will be implemented in which release.

    Tips/Tricks/Cheatsheet to master PMP Exam and Concepts : Youtube Channel

    PMP/Agile Useful Resources : PMP/Agile Resources

    World of Project Management : Mobile App

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.