    Michael is working in an agile environment. Currently, he is working on 2 different projects and is not able to focus properly on both the projects. In terms of Lean, what kind of waste is this?

    a. Task switching
    b. Partially done work
    c. Motion
    d. Waiting

    #22149
    admin
    Keymaster

    Correct answer is A.

    Since Michael would be switching between two projects, this is an example of task switching waste.

    Tips/Tricks/Cheatsheet to master PMP Exam and Concepts : Youtube Channel

    PMP/Agile Useful Resources : PMP/Agile Resources

    World of Project Management : Mobile App

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.