Home Forums PMP Questions and Answers Discussion PMP Question 517

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #22080
    admin
    Keymaster

    An agile team was performing very well till the fourth iteration. However, due to some unforeseen situations, it was not able to complete any story in the fifth iteration. How this situation will effect the burndown chart?

    a. Slope of the burndown chart will become negative
    b. Slope of the burndown chart will become zero
    c. Slope of the burndown chart will become positive
    d. Since the situation was unforeseen so fifth iteration would be cancelled

    #22081
    admin
    Keymaster

    Correct answer is B.

    Since zero story points are completed so the line in the burndown graph would become flat. Thus slope would become zero.

    Tips/Tricks/Cheatsheet to master PMP Exam and Concepts : Youtube Channel

    PMP/Agile Useful Resources : PMP/Agile Resources

    World of Project Management : Mobile App

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.