    An Agile team is facing too many issues to be handled. They want to prioritize issues so that they can focus on high priority issues only. Which technique would be useful to them?

    a. Dot Voting
    b. Triple Nickel
    c. Planning Poker
    d. Fishbone analysis

    #22030
    admin
    Keymaster

    Correct answer is A.

    Dot Voting is an Agile technique to prioritize issues, requirements, etc. Triple Nickel is used to generate ideas in the retrospective. Planning Poker is used for estimation and Fishbone analysis is used for root cause analysis.

    Tips/Tricks/Cheatsheet to master PMP Exam and Concepts : Youtube Channel

    PMP/Agile Useful Resources : PMP/Agile Resources

    World of Project Management : Mobile App

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

    #22033
    Srinivasa
    Guest

    Answer is – Dot Voting, a concept which helps to prioritize issues